Scheduling

All Works Orders (and underlying Sub-Assemblies or Components of an Assembly) are expanded to their constituent Operations and Scheduled using Manufacturing Instruction based Operations and Times are if present - otherwise Quotation details are used.

All these Operation details are then amalgamated, by day, to provide the overviews of Planned vs Available Capacity. Available Capacities are specified through Resource Codes which represent the various Machines or Processes within your company.

Each Resource Code is specified with a Daily Overall Capacity Available (No. of Machines x Normal Working Hours per Day) and Maximum Capacity to be Planned against any one Job per Day (Normal Working Hours per Day).

In addition a Percentage is specified against each day of the week which reflects each days available capacity as a percentage of the Normal Working Hours (e.g. Monday to Thursday may be 100% with Friday being 60% and Saturday being 20% - thus representing a typical early finish on Fridays and Morning Shift on Saturdays).

All Scheduled Works Orders are viewed and monitored from a Works Order Command Screen from which it is possible to see:

  • Planned Start Dates (in RED if late) and Finish Dates
  • Source of Scheduling Data for each W/O (i.e. Manufacturing Instructions or Quotation or Not Scheduled)
  • Drill down to see Customer Order make-up of Works Order
  • Drill Down to see Operation and Time make-up of Works Order
  • Graphical Calendar based Plan showing days when each Operation is Planned and (in a different colour) the Actual Progress alongside
  • Detailed record of Time Bookings to each Operation by Employee
  • Drill Down to all associated Purchase Orders for any Works Order
  • An overview graphical Calendar based Plan of which weeks each W/O is Scheduled
  • A graphical view of Scheduled Requirement for each Resource Group, against available Capacity, that can then be drilled down to see the Planned W/O's for that week

It is also possible to:

  • Re-Schedule an individual Works Order to a different Required Date
  • Print an individual or group of Route Cards

The Major Benefits of this module are:

  • The ability quickly and accurately to calculate and view a plan aqainst which management can plan and prepare their actual production
  • Production of Work To summaries by Resource Code for the Shop Floor Supervisors so they, and their Team, have vision of, and can plan for, work coming through to their Section and its relative importance and priority with other work
  • Customer queries on progress of their Jobs easily answered via the Actual vs Plan graphical display

FactoryMaster have integrated Preactor into their core product for customers who require drag and drop scheduling, We ship a pre configured version of Preactor FCS 200 as standard but customers have the option of upgrading to other versions if they need extra functionallity. FactoryMaster support all versions of Preactor. Customers of FactoryMaster including existing customers can now take advantage of this interface and have the added flexibility of utilising the functionality of a dedicated and highly sophisticated scheduling package.

More information on the FactoryMaster / Preactor link can be found here.